As of November 2026, except the Municipal Code thresholds, findings, appeal periods and permit expiry, which are from the code as it read in August 2022. Rules, forms and fees change. Confirm the current requirements with the City of Sausalito before you rely on anything here.
We are a small architectural firm located in Sausalito. Our office is on Bridgeway, and we have remodeled homes here. If you plan to remodel or add on to a house in Sausalito, the City may need to review the design before it issues a building permit. This guide explains when that review applies, who decides, and what to prepare.
Does your project need design review?
The City says a planning permit is required for almost all changes to a building in Sausalito. It lists fences, decks, windows, doors, room additions, trellises, patio covers and gazebos as exterior changes, and notes that a permit is usually required whether the work is new or a replacement.
The Municipal Code then sorts projects into three paths.
1. Zoning permit only
Projects that fall below the design review thresholds and meet all zoning requirements are exempt from design review. They still need a zoning permit and a building permit.
2. Administrative design review
City staff in the Community Development Department decide these, and the City gives public notice of the application. Examples in the code include:
- An addition to a single-family home or duplex that ends up less than 10 feet from a structure on a neighboring property.
- Cutting or filling that changes the existing grade by more than six feet.
- Fences that require a building permit.
- Terraced or multiple retaining walls that hold back six feet or more of slope within a 10-foot horizontal run.
3. Design Review Permit
The Planning Commission decides these at a public hearing. For an existing single-family home, the code lists projects that:
- Add more than 300 square feet of floor area that creates new building coverage on the lot.
- Add more than 25 percent of the existing floor area or more than 600 square feet, whichever is less, without new building coverage.
- Increase the height of any building.
- Have the potential to impair views from other properties.
A new house, a substantial reconstruction that does not replicate the original, and demolition of 51 percent or more of a house also go to the Planning Commission.
Two points are easy to miss. The size thresholds are counted cumulatively over a three-year period, so a project cannot be split into phases to stay under them. And the last two items on the list do not depend on size at all. A small project that raises a roof or could affect a neighbor’s view is reviewed by the Commission.

What the Planning Commission looks for
The Commission may approve a Design Review Permit only if it can make a set of findings listed in the code. In plain terms, they ask whether the project:
- Is consistent with the General Plan and any design guidelines that apply.
- Complements the neighborhood, either by keeping its prevailing character or by offering a distinctive solution suited to the site.
- Fits the general scale of nearby buildings and does not crowd or overwhelm the neighbors.
- Is located and designed to minimize obstruction of public views and of primary views from private property.
- Avoids a prominent silhouette above a ridgeline.
- Provides adequate light, air and a reasonable level of privacy for the site and for adjacent properties.
- Preserves protected trees and significant natural features to a reasonable extent.
Views carry real weight. The City’s submittal form asks the site plan to identify the outdoor spaces used by neighboring homes and the neighbors’ windows that have “primary views,” a term the code defines.
There is also a stricter test. When a residential project would exceed 80 percent of the floor area or building coverage allowed on the lot, the code calls for “heightened review.” It says the development standards “are not entitlements,” and the decision-maker must determine whether the site can support that much building.
Story poles
Story poles are poles and tape set up on site to outline a proposed building or addition at full size, so neighbors and the Commission can see its height and bulk. The City’s current submittal form sets out the rules:
- A story pole plan is required when there is any change in building footprint, roof elevation or building bulk.
- The poles are certified by a registered land surveyor or civil engineer.
- Bright colored tape connects the poles to outline the roof form.
- The poles go up at least ten days before the noticed public hearing and come down 10 days after a final approval or denial.
- The poles are marked in one-foot increments.
The form adds that protected trees may not be altered or removed to put up story poles without a tree permit.
What you submit
All planning submittals in Sausalito are digital. The City’s Planning Application Submittal Requirements list what a complete application contains. For a residential design review, expect to prepare:
- A dated narrative letter that describes the project and gives the reasons for the design.
- A written explanation of how each required finding can be made.
- A topographic and boundary survey, stamped and signed.
- A site plan showing the nearest structures on adjacent properties and the distances between them.
- Existing and proposed floor plans, elevations and a roof plan, shown side by side, with heights measured from average natural grade.
- Sections through the site that show neighboring structures and the effect on views.
- A demolition plan with calculations of what is removed and what remains.
- A preliminary grading and drainage plan prepared by a registered professional engineer.
- A landscape plan, a digital colors and materials board, and photographs.
- A geological or soils report where the City Engineer requires one, and an arborist report when protected trees are affected.
Fees are set by the City’s Master Fee Schedule. The applicant also signs a cost recovery agreement to pay the City’s actual costs of processing the application.
Talk to the neighbors first
The City’s form says outreach to surrounding property owners before you submit is “strongly recommended, but not required.” We agree with the recommendation. A conversation over the drawings often shows where a roofline or a window could be adjusted before anyone has taken a position at a hearing.
This is part of our work. During planning department submission we act as a liaison and facilitate respectful meetings with city officials and adjacent property owners, to help move the project through the planning department.

Older and historic houses
If the project alters the exterior of a structure more than 50 years old, the City may ask for a Historical Resource Determination packet. A property on the local, state or national historic register, or within a Historic Overlay District, also needs a Certificate of Appropriateness. That covers any change to the exterior appearance, paint color included. The Historic Preservation Commission reviews those applications, and the two commissions regularly hold joint meetings.
The hearing and after
The five-member Planning Commission typically meets twice a month, on Wednesdays at 6:30 p.m., in the Council Chambers at City Hall, 420 Litho Street. Meetings are open to the public.
A Planning Commission decision on a Design Review Permit may be appealed to the City Council within 10 days. A staff decision on an administrative design review may be appealed to the Planning Commission within 10 days. An approved permit expires two years after its effective date unless an extension is filed, and one extension of up to one year may be granted.
Where to start
Before any drawings are finished, find out which path applies. The Planning Division’s counter is open for drop-in questions on Monday, Tuesday and Wednesday mornings, and it offers virtual appointments. The City also has a Planning Permit Process Inquiry form for exactly this question.
On our side, the work starts with pre-design: site analysis, a feasibility study and the selection of consultants such as surveyors and geotechnical engineers. We then develop schematic designs within the zoning requirements.
Questions and answers
Does every remodel in Sausalito need design review?
No. Projects below the code’s thresholds that meet all zoning requirements need only a zoning permit and a building permit. An addition, a taller roof or a possible effect on a neighbor’s view can each bring a project into design review. The Planning Division confirms which path applies.
Who decides a design review application in Sausalito?
City staff decide administrative design review. The Planning Commission decides Design Review Permits at a public hearing. The Community Development Director may also refer an administrative application to the Commission.
When do story poles have to go up?
At least ten days before the noticed public hearing, according to the City’s current submittal form. They are certified by a registered land surveyor or civil engineer, and they are removed 10 days after a final decision.
How long does design review take in Sausalito?
The City pages we reviewed do not give a standard timeline. The time depends on how complete the application is, on the Planning Commission’s calendar and on whether anyone appeals. Ask the Planning Division about current scheduling when you meet with them.
Sources
All read on November 14, 2026, except where noted.
- City of Sausalito, Planning Permits
- City of Sausalito, Planning Permit Forms & Guidelines, including the Planning Permit Application Submittal Requirements and the Story Pole Requirements and Certification Form
- City of Sausalito, Planning Division
- City of Sausalito, Planning Commission and Historic Preservation Commission
- Sausalito Municipal Code, Title 10, Zoning, Chapter 10.54, Design Review Procedures (thresholds, findings, appeal periods and permit expiry read from a copy archived in August 2022)
Planning a project in Sausalito?
See our services, or the Monte Mar and Johnson projects in Sausalito. Then contact us and tell us about your house.
Phil Rossington founded Rossington Architecture in 1999. We work throughout the Bay Area from our office in Sausalito. About the firm.